By Fraser Williams MRICS, Co-Founder and CEO, Morgan Pryce
Direct answer: Begin an office relocation review around 12 months before your required move date, and earlier for larger or more complex requirements. That gives you time to set the brief, test the market, negotiate, design the workplace and manage the move without compromising the commercial outcome.
Why does the timeline matter so much?
An office move should run like any other well-managed business decision, rather than as a race against an expiry date. Time creates options; pressure removes them.
A relocation affects far more than property. It touches people, clients, technology, finance, brand and leadership time, and while the move itself is the visible moment, the important work happens well before it.
The most avoidable mistake is letting a lease expiry or break date become the entire timetable. When time is short the market knows it, your negotiating position weakens, the search narrows and practical decisions get made in a hurry.
Months 12 to 10: define the business case
Start with the leadership team. Clarify what is changing, why it matters and what success looks like, then review headcount, working patterns, client access, recruitment, budget, location, technology and the culture you want the workplace to support.
Assess the existing lease at this stage too, because a relocation strategy is stronger when renewal remains a credible alternative.
Months 10 to 8: build the brief and test the market
Turn the business case into a clear search brief covering locations, size range, space type, budget, timing and non-negotiables. Then test the market widely enough to understand the real choices, including conventional, managed and flexible routes where they fit.
This is the stage for learning rather than committing, and the aim is to come out of it with a well-informed shortlist and a credible negotiating position.
Months 8 to 6: shortlist and negotiate
View, compare and challenge the shortlist against the priorities you agreed at the start. The best office will not necessarily have the best reception, so weigh up total cost, commute, amenity, the quality of the landlord or operator, technical suitability, lease flexibility and what daily life will feel like for the team.
Open negotiations with alternatives still in play, and make sure the commercial terms and heads of terms reflect the whole requirement rather than the rent alone.
Months 6 to 3: legal, design and delivery
Once you have chosen a property, legal work, space planning, IT, fit-out and move planning need to run together in a coordinated way. Technical questions should not be left hanging at this point, and everyone involved, from advisers and lawyers to project managers, IT providers and internal decision-makers, should know exactly what they are responsible for.
Months 3 to 0: move well and protect the business
Communicate clearly with staff and clients, and manage your exit from the old premises, including final obligations, access, technology and day-one operations. A successful move feels calm to the people going through it, because the difficult work has already been done.
The Morgan Pryce view
Property timing should serve the business rather than control it, so begin early enough to give yourself real choice. A well-planned move can improve cost, talent and client experience at the same time, whereas a rushed one usually hands the advantage to somebody else.
FAQ
Plan for around 12 months for most office relocations, with more time for larger, heavily fitted or complex requirements. Smaller moves into flexible space can happen faster.
Once the direction is clear enough that you can answer the practical questions people will have. Involving staff early in shaping the workplace brief can also improve the final result.
Yes. Keeping renewal as a live alternative leads to better decisions and can strengthen your negotiating position.